Design & Deliver

RPS Group was appointed to design and deliver a rooftop solar pv system for Middlefields Waste Transfer Station through the NEPO Decarbonisation Framework.

Operated by South Tyneside Council, Middlefields Waste Transfer Station plays a vital role in helping local residents recycle and dispose of waste responsibly. The site was identified as part of the Council’s wider commitment to cutting carbon emissions and reaching carbon neutrality by 2030.

Delivery

The main challenge of this contract was completing the installation whilst the waste facility remained fully operational.  Delivery was carefully planned around live operations to ensure recycling and waste transfer activities continued without disruption. In total we installed 1144 solar panels across the available roof space.

The project was delivered to high levels of satisfaction:

“The site management on this project was exceptional — proactive, approachable and consistently focused on keeping everyone safe within a live operational environment. The RPS site manager is one of the best I have worked with and a real credit to the team.”

Tara Heys CMIOSH — Health & Safety Advisor, South Tyneside Council


The outcome

The new  solar pv system at  Middlefields Waste Transfer Station will generate around 465,000 kWh of clean electricity each year, avoiding more than 90 tonnes of carbon annually supporting South Tyneside Council’s Net Zero targets.

Project Details


ADDRESS

Middlefields Waste Transfer Station


CLIENT

South Tyneside Council


WORKS

Decarbonisation

VALUE

£445k







— RELATED CASE STUDIES
Parklands Homes, MH Stainton Homes

Parklands Homes, MH Stainton Homes

The Parklands development by our client, MH Stainton Homes, comprises of three, four, and five bedroom luxury countryside villas set in Caton village within Littledale. The villas are located in an

View Case Study
Barrow Dock Museum ERDF Funded PV Installation

Barrow Dock Museum ERDF Funded PV Installation

Panels were mounted in an ‘on roof configuration using a mounting system which was supplied complete. Panels were butted tight together, wind and snow loading was accounted for using the procedures

View Case Study
Alexandra Road

Alexandra Road

Award winning developer, ‘Adlington in partnership with ‘Bardsley Construction have recently completed an £11.5 million luxury development of 55 retirement apartments at Alexandra Road, just a short

View Case Study


This site uses cookies that enable us to make improvements, provide relevant content, and for analytics purposes. For more details, see our Cookie Policy. By clicking Accept, you consent to our use of cookies.