Manchester City Council – SHDF ASHP-Led Retrofit

We have been appointed principal contractor for Manchester City Council’s largest SHDF-funded retrofit programme of its type. An initial 220-property phase was extended through phases 2 and 3 to over 500 social homes – an ASHP-led whole-house retrofit delivered at scale to PAS 2030 and PAS 2035


Core works included Daikin ASHPs installed alongside cavity wall insulation, loft insulation, ventilation, fascias, soffits and rainwater goods – all to manufacturer instructions under PAS 2030. Every property began with a Pre-Installation Survey and a full PAS 2035 suitability inspection to identify building defects before works started.

We held the Retrofit Designer role, working alongside the client-appointed Retrofit Assessors and Coordinators. Certified commissioning engineers completed handovers through detailed resident demonstrations, using bespoke material
 


Outcomes:
  • Every completed property is now EPC C rated.

  • Residents report monthly bill reductions of up to £200.


Project Details


ADDRESS

North Manchester


CLIENT

Manchester City Council


WORKS

SHDF Retrofit






“We had our heat pump installed by RPS 3 months ago and we’re now saving £40 a month on bills – a huge saving for us as pensioners. RPS have been fantastic – the process was fabulous, with booklets, information and follow-up visits.” 

Marina Street, Manchester City Council Resident 



“RPS have always worked collaboratively and proactively with stakeholders.” 

Elliot Simm, Manchester City Council 



"We have worked with RPS over many years, the projects RPS has delivered with us have been technically difficult, often delivered through externally funded routes — which adds a further layer of complexity and hard targets. RPS has been an integral part of the teams delivering these projects successfully.

Their no-fuss approach makes the installation process as streamlined as possible, and their proactive site teams deliver a good on-site service for residents with minimal complaints. They have been reliable partners  and we would have no hesitation in working with RPS on future projects"

Elliot SimmCommercial, Design and Delivery Team Leader, Manchester City Council




— RELATED CASE STUDIES
Broughton Hub

Broughton Hub

RPS were commissioned by Salford City Council to produce a Stage 3 design package associated with modifications to the heating and hot water systems at the Broughton Hub in Salford in association

View Case Study
Waterloo Street, Newcastle

Waterloo Street, Newcastle

Places for People Group are one of the UKs largest property management, leisure management, development, and regeneration companies. One of our Larger scale customers who own & manage over 148,000

View Case Study
Cronton Sixth Form College

Cronton Sixth Form College

Rothwell Building Services part of RPS Group Ltd has successfully completed work at Cronton Sixth Form College in Widnes on a 320 seat Playhouse Theatre and Brasserie for our client Whitfield & Brown

View Case Study


This site uses cookies that enable us to make improvements, provide relevant content, and for analytics purposes. For more details, see our Cookie Policy. By clicking Accept, you consent to our use of cookies.