Tofts farm depot is the main maintenance hub for Hartlepool Borough Council housing the headquarters for the council’s refuse & recycling operations, as well as the facility being used to service, repair, and test the council’s fleet of over 250 vehicles. This project was selected by Hartlepool Borough Council as part of its decarbonisation programme.
We have successfully installed 277 solar panels to Tofts farm, completed within a 2 week delivery period. The project was delivered In 4 stages:
Stage 1 – Mounting kit installation
Stage 2 – Optimiser installation
Stage 3 – DC cabling
Stage 4 – Panel installation
Following a structured programme ensured a safe and efficient project delivery.
Works on site commenced in February and achieved practical completion in 2 weeks. Our delivery team was made up of 7 operatives in total: 5 undertaking roof works and 2 dedicated to electrical works.
All required components were procured prior to mobilisation, meaning there were no supply delays to impact the programme.
Panels – Longi 535w LR7-60HVD-535W
Inverter – SolarEdge SE100K
Optimisers – 139 × SolarEdge S1000
Mounting – SFlex Trapezoidal Steel Roof Fixing
The pre-installation roof survey identified a number of defects, RPS Group carried out roofing repair works to maximise the operational lifespan of the PV system. This eliminated the need for separate procurement and ensured that the roof repairs and PV installation ran smoothly ahead of project commencement.
Hartlepool Borough Council have a Net Zero target of 2050. SolarEdge remote monitoring was activated prior to work commencement allowing Hartlepool Borough Council to track real time energy production from day one. The installation is set to reduce CO₂ Emissions by 23.62 tonnes/year supporting Hartlepool Borough Council’s aim to improve energy efficiency and increase sustainable energy.
Tofts Farm Depot
Hartlepool Borough Council
Solar PV installations
RPS Group has partnered with Southway Housing Trust to undertake the EDRF Arrowfield Decarbonisation Project. The project entailed the replacement of gas boilers with the latest eco-friendly air
View Case StudyHomeserve+ have been undertaking a fully comprehensive heating maintenance contract for South Lakes Housing for nearly 10 years. We cover the service & maintenance for just over 3200 properties of
View Case StudyPeachment Place Rothwell Building Services on behalf of RPS Group Ltd have recently completed work on the ‘Peachment Place project in Bury. The £9.6 million new build development provides one & two
View Case StudyThis site uses cookies that enable us to make improvements, provide relevant content, and for analytics purposes. For more details, see our Cookie Policy. By clicking Accept, you consent to our use of cookies.